Certain Motor Control Center (MCC) equipment production for the improvements project was delayed and Woodruff Construction received confirmation from the manufacturer on a production scheduled that did not include further delays. Since receiving the schedule Woodruff Construction requested a time extension under article 4.05-C of the Contract General Conditions for no change in contract price. Change Order #1 revised the contract time providing 190 day extensions to Milestone No. 1 Completion, Substantial Completion, and Final Completion, as follows: Comments are closed.
|